Public contracts of Communauté d'agglomération de Lens - Liévin · 2023
Finitions
€43k
contract ceiling — what was paid on it is not published
Who won it
Trione ConstructionConstruction d'autres bâtiments · registered office Houdain (62150) · headcount 20 to 49 employees · SIREN 792517682Number 51 by amount of the 66 contracts Communauté d'agglomération de Lens - Liévin published for 2023.
Other contracts of Trione Construction in Communauté d'agglomération de Lens - Liévin
Construction d’un restaurant scolaire et accueil périscolaire rue Paul…202615.9€MConstruction d’un restaurant scolaire et accueil périscolaire rue Paul…2025150€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.