Public contracts of Communauté d'agglomération de Nevers · 2023
Dévoiement du réseau fibre
Centre des expositions
Company selected
Ineo Réseaux Nord EstConstruction de réseaux électriques et de télécommunications · registered office Dijon (21000) · headcount 250 to 499 employees · SIREN 381287101Number 40 by amount of the 52 contracts Communauté d'agglomération de Nevers published for 2023.
Other contracts of Ineo Réseaux Nord Est in Communauté d'agglomération de Nevers
Travaux de dévoiement du réseau fibre pour le centre des expositions de…2023 · maximum over 1 month53€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Ferme
Published amendments : 1