Skip to main content

Public contracts of Communauté d'agglomération de Nîmes Métropole · 2022

Déploiement d’un réseau bas débit et acquisition d’objets connectés

€880k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 30 May 2022 · ended around May 2026 · 4 yrs

That is at most ~€220k a year on average: a maximum too.

Who won it

Ineo InfracomConstruction de réseaux électriques et de télécommunications · registered office Dijon (21000) · headcount 1,000 to 1,999 employees · SIREN 409867942

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Synox. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 19 by amount of the 127 contracts Communauté d'agglomération de Nîmes Métropole published for 2022.

Other contracts of Ineo Infracom in Communauté d'agglomération de Nîmes Métropole

Fourniture, installation et maintenance des dispositifs de sûreté /…2026 · maximum over 10 months460€kTravaux de câblage VDI et courant fort2026 · maximum over 4 years32€kExtension et maintenance du dispositif de vidéosurveillance2022 · maximum over 4 years8.6€M
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Mixte

Published amendments : 5

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.