Skip to main content

Public contracts of Communauté d'agglomération de Saint-Dié-des-Vosges · 2021

Fourniture d’électricité

Électricité Sites BT

€232k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 27 October 2021 · ended around October 2025 · 4 yrs

That is at most ~€58k a year on average: a maximum too.

Company selected

Électricité de FranceProduction d'électricité · registered office Paris (75008) · headcount 10,000 employees or more · SIREN 552081317

A contract awarded to 3 holders; above, the main holder. With it: Total Direct Énergie Solutions, Union des Producteurs Locaux d'Électricité (Énergie d'Ici). The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 5 by amount of the 33 contracts Communauté d'agglomération de Saint-Dié-des-Vosges published for 2021.

Other contracts of Électricité de France in Communauté d'agglomération de Saint-Dié-des-Vosges

Électricité2023 · maximum over 1 month153€kFourniture d’électricité pour le2022 · maximum over 12 months279€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.