Skip to main content

Public contracts of Communauté d'agglomération du Bassin de Brive · 2024

Mise en conformité du système d’assainissement de la commune de saint-cyr-la-roche

€530k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 4 November 2024 · ended around November 2025 · 12 months

Who won it

Établissements Miane et VinatierConstruction de réseaux pour fluides · registered office Brive La Gaillarde (19100) · headcount 50 to 99 employees · SIREN 675520241

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 7 by amount of the 36 contracts Communauté d'agglomération du Bassin de Brive published for 2024.

Other contracts of Établissements Miane et Vinatier in Communauté d'agglomération du Bassin de Brive

Mise en conformité du système d’assainissement de la commune de…2024 · maximum over 10 months257€kTravaux de renouvellement des réseaux d’eau potable…2022 · maximum over 5 months545€kSécurisation et amélioration des ouvrages d’eau potable de la CABB…2021 · maximum over 7 months201€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

The 3 lots : 324 €k · 129 €k · 78 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Mise en conformité du système d’assainissement de la commune de…: up to €530k over 12 months, Communauté d'agglomération du Bassin de Brive 2024 · Qipu