Maîtrise d’œuvre relative à la création de la passerelle Modock Bissol, à Fort-de-France

€100k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 7 May 2026 · running until about May 2028 · 2 yrs
Ongoing7 May 2028

That is at most ~€50k a year on average: a maximum too.

Who won it

Architecture NeelSIREN 392294120

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Antea France. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

8 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 24 by amount of the 32 contracts Communauté d'agglomération du Centre de la Martinique published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Social considerations : Clause sociale

Environmental considerations : Clause environnementale