Travaux de renouvellement du réseau d’eau potable sur la commune de Domezain-Berraute

RD11 – Programme 2023

€415k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 15 February 2024 · ended around July 2024 · 5 months

Who won it

Canalisations Travaux Publics SocatpSIREN 382839066

Number 47 by amount of the 163 contracts Communauté d'agglomération du Pays Basque published for 2024.

Other contracts of Canalisations Travaux Publics Socatp in Communauté d'agglomération du Pays Basque

Bidache quartier port extension rseaux EU + AEP2025 · maximum over 1 month483€kBidache quartier port extension EU + création pr2025 · maximum over 1 month65€kLes aldudes eznazu renouvellement AEP2024 · maximum over 1 month749€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.