Skip to main content

Public contracts of Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR) · 2025

Maîtrise d’œuvre voirie et réseaux divers pour les infrastructures dédiées à l’opération BAOBAB…

€1.5M
framework agreement: a maximum envelope for orders over 7.5 years, not spending — what was paid on it is not published
Signed on 21 October 2025 · running until about January 2033 · 7.5 yrs
Ongoing20 Jan 2033

That is at most ~€203k a year on average: a maximum too.

Who won it

Ingerop Conseil et Ingenierie (Ici)Ingénierie, études techniques · registered office Rueil Malmaison (92500) · headcount 1,000 to 1,999 employees · SIREN 489626135

The competition

4 bids received

Median for this procedure in 2025: 3 bids, across 17964 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 41 by amount of the 316 contracts Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR) published for 2025.

Other contracts of Ingerop Conseil et Ingenierie (Ici) in Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR)

Assistance à maîtrise d’ouvrage renouvelt du contrat d’exploitation…2026 · maximum over 6 months165€kAssistance a maîtrise d’ouvrage dans le cadre de l’elaboration du plan…2022 · maximum over 18 months153€kMission d’études de programmation pour la réalisation d’itinéraires…2022 · maximum over 3 months29€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.