Conception, réalisation et l’intégration d’une salle immersive multisensorielle au sein du parcours existant de l’espace touristique d’interprétation KAZ TUIT…

€100k
contract ceiling — what was paid on it is not published
Signed on 28 May 2026 · running until about March 2027 · 10 months
Ongoing28 Mar 2027

Who won it

TimescopeAutres services de réservation et activités connexes · registered office Paris (75005) · headcount 10 to 19 employees · SIREN 812525780

The competition

2 bids received

Median for this procedure in 2026: 3 bids, across 34631 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 115 by amount of the 179 contracts Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR) published for 2026.

Other contracts of Timescope in Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR)

Services et fournit pour réal.et l’intégration technol Kaz Tuit Tuit2025177€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Environmental considerations : Critère environnemental