Skip to main content

Public contracts of Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR) · 2024

Travaux renouvellement réseau refoulement pr Ango ss

€1.5M
maximum contract amount over 13 months — what was paid on it is not published
Signed on 29 November 2024 · ended around December 2025 · 13 months

That is at most ~€1.4M a year on average: a maximum too.

Who won it

HydrotechConstruction de réseaux pour fluides · registered office La Possession (97419) · headcount 100 to 199 employees · SIREN 381605583

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Bâtiments Travaux Ocean Indien (Enrobes Reunion). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 2 by amount of the 169 contracts Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR) published for 2024.

Other contracts of Hydrotech in Communauté d'agglomération Intercommunale du Nord de la Réunion (CINOR)

TRAV réhab EU quartier carricube2026 · maximum over 10 months596€kTRAVX de construct et de réhabilitation sur les réseaux publics EPU…2025 · maximum over 4 years2.1€MChemin dufourg les hauts2025 · maximum over 10 months1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 3

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.