Skip to main content

Public contracts of Communauté d'agglomération Lannion-Trégor Communauté · 2024

Maîtrise d’œuvre pour la création ou la réhabilitation de poste de relèvement pour le service Eau et Assainissement de…

€20k
framework agreement: a maximum envelope for orders over 2 years, not spending — what was paid on it is not published
Signed on 15 February 2024 · ended around March 2026 · 2 yrs

That is at most ~€10k a year on average: a maximum too.

Who won it

Okare IngenierieIngénierie, études techniques · registered office Cesson-Sevigne (35510) · headcount 20 to 49 employees · SIREN 511617029

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 51 by amount of the 56 contracts Communauté d'agglomération Lannion-Trégor Communauté published for 2024.

Other contracts of Okare Ingenierie in Communauté d'agglomération Lannion-Trégor Communauté

Maîtrise d’œuvre relative à la Construction de la station d’épuration…2024 · maximum over 4 years66€kMaîtrise d’œuvre réhab 3 pr Lannion2023 · maximum over 2 years25€kÉtudes techniques et règlementaires pour le service Eau…2023 · maximum over 2 months21€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.