Skip to main content

Public contracts of Communauté d'agglomération Les Sables d'Olonne Agglomération · 2023

Maîtrise d’œuvre réfection parapet promenade godet

€77k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 17 February 2023 · ended around May 2024 · 15 months

That is at most ~€61k a year on average: a maximum too.

Company selected

ArteliaIngénierie, études techniques · registered office Saint-Ouen-Sur-Seine (93400) · headcount 2,000 to 4,999 employees · SIREN 444523526

Number 26 by amount of the 36 contracts Communauté d'agglomération Les Sables d'Olonne Agglomération published for 2023.

Other contracts of Artelia in Communauté d'agglomération Les Sables d'Olonne Agglomération

Maîtrise d’œuvre pour la remise en état de l’ecluse de la bauduere2025 · maximum over 2 years76€kMaîtrise d’oeuvre2021 · maximum over 12 months45€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.