Public contracts of Communauté d'agglomération Lorient Agglomération · 2026
Maîtrise d’œuvre partielle relative aux travaux d’isolation et d’étanchéité sous bardage de la Cité de la Voile
That is at most ~€43k a year on average: a maximum too.
Company selected
AIA ArchitectesActivités d'architecture · registered office Nantes (44100) · headcount 200 to 249 employees · SIREN 316173160The competition
Median for this procedure in 2026: 3 bids, across 23502 comparable contracts. Simplified procedure · awarded to 1 company
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 96 by amount of the 136 contracts Communauté d'agglomération Lorient Agglomération published for 2026.
Other contracts of AIA Architectes in Communauté d'agglomération Lorient Agglomération
Maîtrise d’œuvre pour la modernisation du Parc des Expositions à…2024 · maximum over 4.5 years1.2€MContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.