Construction d’une Maison d’Assistantes Maternelles à Sennecé-lès-Mâcon

Gros oeuvre

€880
contract ceiling — what was paid on it is not published
Signed on 31 October 2025 · running until about August 2027 · 21 months
Ongoing1 Aug 2027

Who won it

Bourdon ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Cyr-Sur-Menthon (01380) · headcount 20 to 49 employees · SIREN 453193799

The competition

62 bids received

Median for this procedure in 2025: 3 bids, across 49224 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 157 by amount of the 162 contracts Communauté d'agglomération Mâconnais Beaujolais Agglomération published for 2025.

Other contracts of Bourdon Construction in Communauté d'agglomération Mâconnais Beaujolais Agglomération

Gros œuvre202686€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.