Skip to main content

Public contracts of Communauté d'agglomération Marne et Gondoire · 2025

Travaux d’assainissement de la rue du maréchal gallieni a thorigny-sur-Marne

€2.8M
maximum contract amount over 13 months — what was paid on it is not published
Signed on 5 June 2025 · ended around July 2026 · 13 months

That is at most ~€2.6M a year on average: a maximum too.

Who won it

Travaux Publics Ile de FranceConstruction de réseaux pour fluides · registered office Lagny-Sur-Marne (77400) · headcount 20 to 49 employees · SIREN 344877808

The competition

4 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 6 by amount of the 28 contracts Communauté d'agglomération Marne et Gondoire published for 2025.

Other contracts of Travaux Publics Ile de France in Communauté d'agglomération Marne et Gondoire

Reconstruction des ouvrages du système d’endiguement du quai du pré…2025 · maximum over 8 months827€kReconstruction des ouvrages du système d’endiguement du quai du pré…2025 · maximum over 2.5 years827€kTravaux d’assainissement du quartier clos richard ouest a dampmart2024 · maximum over 10 months1.9€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.