Skip to main content

Public contracts of Communauté d'agglomération Moulins Communauté · 2019

Franchissement de l’Allier par le réseau d’assainissement

Reconnaissances géotechniques

€28k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 27 November 2019 · ended around February 2020 · 3 months

Who won it

GeotecIngénierie, études techniques · registered office Quetigny (21800) · headcount 500 to 999 employees · SIREN 778196501

Number 38 by amount of the 46 contracts Communauté d'agglomération Moulins Communauté published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.