Travaux de dévoiement de réseau d’eau potable pour le franchissement de l’allier a Moulins

Canalisations

€60k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 25 October 2023 · ended around February 2024 · 4 months

Who won it

Eurovia Drome Ardeche Loire AuvergneConstruction de routes et autoroutes · registered office Saint-Jean-Bonnefonds (42650) · headcount 500 to 999 employees · SIREN 317975910

The competition

5 bids received

Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 25 by amount of the 36 contracts Communauté d'agglomération Moulins Communauté published for 2023.

Other contracts of Eurovia Drome Ardeche Loire Auvergne in Communauté d'agglomération Moulins Communauté

Rue Régemortes2025 · maximum over 2 months246€kAménagement des berges de l’allier entre le pont regemortes…2024 · maximum over 12 months1.8€MRéhabilitation de l’Aire d’accueil des Gens du Voyage d’Yzeure2024 · maximum over 11 months225€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.