Public contracts of Communauté d'agglomération Saint-Brieuc Armor Agglomération · 2022

Travaux sur le système d’assainissement de Saint-Carreuc

Station d’épuration

€1.3M
maximum contract amount over 18 months — what was paid on it is not published
Signed on 18 July 2022 · ended around January 2024 · 18 months

That is at most ~€842k a year on average: a maximum too.

Company selected

SaurCaptage, traitement et distribution d'eau · registered office Issy-Les-Moulineaux (92130) · headcount 5,000 to 9,999 employees · SIREN 339379984

The competition

5 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 28 contracts Communauté d'agglomération Saint-Brieuc Armor Agglomération published for 2022.

Other contracts of Saur in Communauté d'agglomération Saint-Brieuc Armor Agglomération

Travaux d’amélioration de l’usine de production d’eau potable du…2026 · maximum over 8.5 years309€kLes lagunages de la commune de LANTIC, en service depuis plusieurs…2024 · maximum over 2.5 years210€kLes prestations demandées sont les suivantes2024 · maximum over 17 months156€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.