Réhabilitation de la friche Pierron à Sarreguemines pour la construction des ateliers eau/assainissement et du nouveau chantier d’insertion

€54k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 21 February 2023 · ended around August 2024 · 18 months

That is at most ~€36k a year on average: a maximum too.

Company selected

Société Hornberger et FilsTravaux de peinture et vitrerie · registered office Goetzenbruck (57620) · headcount 10 to 19 employees · SIREN 302070339

The competition

4 bids received

Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 86 by amount of the 105 contracts Communauté d'agglomération Sarreguemines Confluences published for 2023.

Other contracts of Société Hornberger et Fils in Communauté d'agglomération Sarreguemines Confluences

Réhabilitation friche pierron2023 · maximum over 18 months65€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 4

Subcontracting declared : no