Travaux de rafraichissement des crèches de la Communauté d'agglomération Sarreguemines Confluences

€93k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 6 June 2024 · ended around September 2024 · 3 months

Who won it

Starck ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Theding (57450) · headcount 20 to 49 employees · SIREN 323735662

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 30 by amount of the 96 contracts Communauté d'agglomération Sarreguemines Confluences published for 2024.

Other contracts of Starck Électricité in Communauté d'agglomération Sarreguemines Confluences

2025038 Déferrisation et demanganisation forage SEB2 a SGMS2025 · maximum over 11 months464€kRéhabilitation de la friche Pierron à Sarreguemines…2023 · maximum over 18 months217€kTravaux espace entreprise2022 · maximum over 6 months92€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale