Skip to main content

Public contracts of Communauté d'agglomération Territoire de la Côte Ouest (TCO) · 2025

Ouvrages de lutte contre la submersion marine et l’érosion côtière du TCO

€2.5M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 23 January 2025 · running until about January 2029 · 4 yrs
Ongoing23 Jan 2029

That is at most ~€625k a year on average: a maximum too.

Company selected

B.R.L.INGENIERIEIngénierie, études techniques · registered office Nimes (30000) · headcount 200 to 249 employees · SIREN 391484862

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 17964 comparable contracts. Open tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 12 by amount of the 97 contracts Communauté d'agglomération Territoire de la Côte Ouest (TCO) published for 2025.

Other contracts of B.R.L.INGENIERIE in Communauté d'agglomération Territoire de la Côte Ouest (TCO)

Système d’endiguement de la Rivière des Galets2025 · maximum over 4 years6€MOuvrages de lutte contre la submersion marine…2025 · maximum over 4 years2€Maîtrise d’œuvre pour la valorisation écologique…2024 · maximum over 4 years89€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : 2

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.