Public contracts of Communauté d'agglomération Troyes Champagne Métropole · 2021

Travaux remise en état clarificateurs STEP barberey

€889k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 20 May 2021 · ended around August 2022 · 15 months

That is at most ~€711k a year on average: a maximum too.

Who won it

La Mecano Soudure de ConceptionSIREN 828812776

Number 13 by amount of the 60 contracts Communauté d'agglomération Troyes Champagne Métropole published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.