Public contracts of Communauté d'agglomération Val de Garonne Agglomération · 2024

Réhabilitation du centre de loisirs de Marmande

Chauffage, ventilation, climatisation Plomberie

€320k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 14 March 2024 · ended around August 2026 · 2.5 yrs

That is at most ~€132k a year on average: a maximum too.

Company selected

Établissements Rigo Jean PierreTravaux d'installation d'équipements thermiques et de climatisation · registered office Sainte-Bazeille (47180) · headcount 20 to 49 employees · SIREN 408415248

The competition

26 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 29 by amount of the 71 contracts Communauté d'agglomération Val de Garonne Agglomération published for 2024.

Other contracts of Établissements Rigo Jean Pierre in Communauté d'agglomération Val de Garonne Agglomération

Chauffage, ventilation, climatisation plomberie2024 · maximum over 2.5 years315€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.