Skip to main content

Public contracts of Communauté d'agglomération Vitré Communauté · 2022

Construction du centre aquatique communautaire de La Guerche de Bretagne

Menuiseries intérieures bois

€381k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 31 March 2022 · ended around September 2023 · 18 months

That is at most ~€254k a year on average: a maximum too.

Company selected

Heude BâtimentTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Ernee (53500) · headcount 50 to 99 employees · SIREN 378008924

The competition

50 bids received

Median for this procedure in 2022: 4 bids, across 2484 comparable contracts. Open tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 75 contracts Communauté d'agglomération Vitré Communauté published for 2022.

Other contracts of Heude Bâtiment in Communauté d'agglomération Vitré Communauté

Travaux de réhabilitation et de restructuration du site de Château Marie2025 · maximum over 2 years319€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.