Construction du centre aquatique communautaire de La Guerche de Bretagne

Des lots 4, 5, 8, 18 et 19 après déclaration Courants forts · Courants faibles

€648k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 31 March 2022 · ended around September 2023 · 18 months

That is at most ~€432k a year on average: a maximum too.

Company selected

Elitel ÉnergiesTravaux d'installation électrique dans tous locaux · registered office Change (53810) · headcount 10 to 19 employees · SIREN 443473731

The competition

12 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 8 by amount of the 75 contracts Communauté d'agglomération Vitré Communauté published for 2022.

Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : 4

Subcontracting declared : no