Travaux de réhabilitation et de restructuration du site de Château Marie

Carrelage · Faïence

€84k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 22 July 2025 · running until about November 2027 · 2.5 yrs
Ongoing21 Nov 2027

That is at most ~€36k a year on average: a maximum too.

Company selected

Barbot CarrelageTravaux de revêtement des sols et des murs · registered office Vitre (35500) · headcount 6 to 9 employees · SIREN 389595208

The competition

4 bids received

Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 60 by amount of the 110 contracts Communauté d'agglomération Vitré Communauté published for 2025.

Other contracts of Barbot Carrelage in Communauté d'agglomération Vitré Communauté

Réhabilitation et remise en état de la piscine Aquatide2025 · maximum over 12 months138€kRevêtement de sols durs et muraux piscine aquatide2025 · maximum over 1 month137€kCarrelage faïence réhabilitation château marie2025 · maximum over 1 month88€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.