Public contracts of Communauté de communes Arc Sud Bretagne · 2023

Missions de maîtrise d’oeuvre pour les travaux d’aménagement du nouveau centre technique communautaire

€120k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 17 January 2023 · ended around March 2025 · 2 yrs

That is at most ~€55k a year on average: a maximum too.

Who won it

Bureau d'Études LegavreIngénierie, études techniques · registered office Theix-Noyalo (56450) · headcount 1 or 2 employees · SIREN 347446437

A contract awarded to a consortium of 5 holders; above, the main holder. With it: Kaso Atelier d'Architecture, Bureau d'Etude Cooperatif pour la Maitrise de l'Énergie 56 (Become 56), Atlantique Loire Structure, 107 Eco. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 16 by amount of the 33 contracts Communauté de communes Arc Sud Bretagne published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.