Démolition

GORS oeuvre · Étanchéité

€866k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 12 February 2026 · running until about June 2027 · 16 months
Ongoing14 Jun 2027

That is at most ~€650k a year on average: a maximum too.

Who won it

Entreprise Diaz Joel et FilsTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Viviers (07220) · headcount 10 to 19 employees · SIREN 452055726

Number 3 by amount of the 20 contracts Communauté de communes Ardèche Rhône Coiron published for 2026.

Other contracts of Entreprise Diaz Joel et Fils in Communauté de communes Ardèche Rhône Coiron

Démolition gros oeuvre étanchéité2026 · maximum over 16 months1.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.