Public contracts of Communauté de communes Auxonne Pontailler Val de Saône · 2026

Interconnexion eau potable

Villers/Auxonne

€1.3M
framework agreement: a maximum envelope for orders over 6 months, not spending — what was paid on it is not published
Signed on 10 July 2026 · running until about January 2027 · 6 months
Ongoing9 Jan 2027

Company selected

Sade - Compagnie Générale de Travaux HydrauliquesConstruction de réseaux pour fluides · registered office Paris (75014) · headcount 2,000 to 4,999 employees · SIREN 562077503

The competition

3 bids received

Median for this procedure in 2026: 3 bids, across 253 comparable contracts. Restricted tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 19 contracts Communauté de communes Auxonne Pontailler Val de Saône published for 2026.

Other contracts of Sade - Compagnie Générale de Travaux Hydrauliques in Communauté de communes Auxonne Pontailler Val de Saône

Mise en séparatif du réseau assainissement2026 · maximum over 9 months1.1€MMise en séparatif du réseau eau potable2026 · maximum over 9 months357€kRéhabilitation conduite assainissement2026 · maximum over 6 months330€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres restreint

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.