CFA de l’aménagement de la Maison de la Nature à Neuvry

Électricité CFO

€70k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 20 October 2025 · running until about November 2026 · 13 months
Ongoing20 Nov 2026

That is at most ~€65k a year on average: a maximum too.

Who won it

Soc ChastragnatTravaux d'installation électrique dans tous locaux · registered office Montereau-Fault-Yonne (77130) · headcount 6 to 9 employees · SIREN 353803786

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 18 by amount of the 29 contracts Communauté de communes Bassée-Montois published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.