Skip to main content

Public contracts of Communauté de communes Bazois Loire Morvan · 2026

Couverture zinc et zinguerie crèche fours

€84k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 31 March 2026 · running until about January 2027 · 10 months
Ongoing29 Jan 2027

Company selected

EURL RiotteTravaux de couverture par éléments · registered office Sancoins (18600) · headcount 6 to 9 employees · SIREN 484547393

The competition

7 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 18 contracts Communauté de communes Bazois Loire Morvan published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.