Public contracts of Communauté de communes Bretagne Romantique · 2026

Maîtrise d’oeuvre pour la réhabilitation du complexe sportif communautaire de combourg

€216k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 31 March 2026 · running until about January 2028 · 22 months
Ongoing30 Jan 2028

That is at most ~€118k a year on average: a maximum too.

Who won it

Acoustique & ConseilIngénierie, études techniques · registered office Paris (75010) · headcount 20 to 49 employees · SIREN 328641154

A contract awarded to a consortium of 6 holders; above, the main holder. With it: Ouest Structures, Cabinet Lemonnier SARL, Alta le Trionnaire le Chapelain, Solab, ELEMENT.EXE. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

23 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 6 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 3 by amount of the 25 contracts Communauté de communes Bretagne Romantique published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.