Public contracts of Communauté de communes Brocéliande Communauté · 2022

Travaux pour la construction d’un établissement d’accueil de jeunes enfants (EAJE)

Cloisons sèches · Plafonds · Isolation

€119k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 23 March 2022 · ended around March 2023 · 12 months

Who won it

Armor RenovationTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Breal-Sous-Montfort (35310) · headcount 6 to 9 employees · SIREN 419128657

The competition

35 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 12 by amount of the 32 contracts Communauté de communes Brocéliande Communauté published for 2022.

Other contracts of Armor Renovation in Communauté de communes Brocéliande Communauté

Travaux de construction d’une base VTT TRIAL…2025 · maximum over 10 months19€kNo title given2022 · maximum over 12 months121€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no