Skip to main content

Public contracts of Communauté de communes Bugey Sud · 2026

Conception réalisation Travaux réhab STEP Culoz-Beon

€3.4M
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 3 August 2026 · running until about March 2029 · 2.5 yrs
Ongoing4 Mar 2029

That is at most ~€1.3M a year on average: a maximum too.

Company selected

Systeme WolfConstruction d'ouvrages d'art · registered office Leutenheim (67480) · headcount 200 to 249 employees · SIREN 301467056

A contract awarded to 4 holders; above, the main holder. With it: Artelia, Sade - Compagnie Générale de Travaux Hydrauliques, Zeppelin Architectes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 19 contracts Communauté de communes Bugey Sud published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.