Public contracts of Communauté de communes Bugey Sud · 2020
Construction d’un réservoir de 1200 m3 à Champeillon
Commune de BELLEY · Canalisations
Who won it
Dumas T.P.Travaux de terrassement courants et travaux préparatoires · registered office Chazey-Bons (01300) · headcount 20 to 49 employees · SIREN 343620662Number 15 by amount of the 24 contracts Communauté de communes Bugey Sud published for 2020.
Other contracts of Dumas T.P. in Communauté de communes Bugey Sud
Travaux renounvelmt conduite AEP four grammont202656€kTravaux eau potable et assainissement a virignin20252.6€MAccord-cadre a bc travaux de voirie20252€MContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.