Travaux de requalification de l’entrée de PIA

€1.4M
maximum contract amount over 8 months — what was paid on it is not published
Signed on 2 August 2019 · ended around April 2020 · 8 months

Who won it

—Construction de routes et autoroutes · registered office Toulouse (31100) · headcount 1,000 to 1,999 employees · SIREN 302698873

A contract awarded to 2 holders; above, the main holder. With it: Travaux Publics 66. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 39 contracts Communauté de communes Corbières Salanque Méditerranée published for 2019.

Other contracts of in Communauté de communes Corbières Salanque Méditerranée

Création zone technique et extension parking agents2022 · maximum over 5 months383€kTravaux d’extension et de réaménagement des espaces extérieurs du siège…2022 · maximum over 5 months351€kTravaux d’aménagement du chemin de saint pierre a claira2021 · maximum over 1 month53€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.