Skip to main content

Public contracts of Communauté de communes Cœur de Garonne · 2019

Travaux de construction d’un gymnase à Cazères sur Garonne

€1M
maximum contract amount over 15 months — what was paid on it is not published
Signed on 23 September 2019 · ended around December 2020 · 15 months

That is at most ~€831k a year on average: a maximum too.

Company selected

Générale de Bâtiment Midi PyrénéesConstruction d'autres bâtiments · registered office Tournefeuille (31170) · headcount 250 to 499 employees · SIREN 420254807

Number 2 by amount of the 66 contracts Communauté de communes Cœur de Garonne published for 2019.

Other contracts of Générale de Bâtiment Midi Pyrénées in Communauté de communes Cœur de Garonne

Travaux de construction d’un gymnase a cazeres sur Garonne2019 · maximum over 23 months1.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.