Skip to main content

Public contracts of Communauté de communes Cœur de Loire · 2024

Travaux de restauration du réseau de mares à Triton marbré de la forêt de Bellary

€13k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 2 August 2024 · ended around November 2024 · 3 months

Who won it

Mario et LongoTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Premery (58700) · headcount 10 to 19 employees · SIREN 701880023

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 25 by amount of the 27 contracts Communauté de communes Cœur de Loire published for 2024.

Other contracts of Mario et Longo in Communauté de communes Cœur de Loire

Travaux de restauration des cours d’eau2024 · maximum over 2.5 years133€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Travaux de restauration du réseau de mares à Triton marbré de la…: up to €13k over 3 months, Communauté de communes Cœur de Loire 2024 · Qipu