Public contracts of Communauté de communes de l'Alta Rocca · 2019
Mission complète de maîtrise d’oeuvre pour la restructuration et l’extension de l’ancienne gendarmerie de Levie
That is at most ~€7k a year on average: a maximum too.
Who won it
SCDF Giusti Eric Versini AntoineSIREN 340345115A contract awarded to 2 holders; above, the main holder. With it: Structures Informatique Électricité Thermique Ingenierie et Conseils. The amount is the whole contract’s: the DECP does not publish each holder’s share.
Number 13 by amount of the 14 contracts Communauté de communes de l'Alta Rocca published for 2019.
Contract details (procedure, price, amendments, lots)
Procedure : Procédure avec négociation
Price : Révisable
Published amendments : none
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.