Travaux d’extension basse tension divers secteurs de maripasoula programme 2022

€350k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 5 June 2024 · ended around June 2026 · 2 yrs

That is at most ~€175k a year on average: a maximum too.

Who won it

Getelec GuyaneConstruction de réseaux électriques et de télécommunications · registered office Cayenne (97300) · headcount 50 to 99 employees · SIREN 390870095

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 14 by amount of the 34 contracts Communauté de communes de l'Ouest Guyanais published for 2024.

Other contracts of Getelec Guyane in Communauté de communes de l'Ouest Guyanais

Extension et renforcement des réseaux électriques du bourg de Grand…2022 · maximum over 2 years1€MTravaux pour l’Extension du Réseau de Distribution Électrique du bourg…2022 · maximum over 4 years380€kExtension des réseaux électriques sur les écarts Nord d’Apatou…2022 · maximum over 12 months180€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.