Skip to main content

Public contracts of Communauté de communes de la Grande Vallée de la Marne · 2026

Restauration église Hautvillers

Électricité-Éclairage intérieur extérieure

€211k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 9 June 2026 · running until about November 2028 · 2.5 yrs
Ongoing8 Nov 2028

That is at most ~€87k a year on average: a maximum too.

Company selected

Gtie Cap Infras (Cegelec Chalons Réseaux)Construction de réseaux électriques et de télécommunications · registered office Chateau-Thierry (02400) · headcount 100 to 199 employees · SIREN 414688879

The competition

1 bid received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 6 by amount of the 13 contracts Communauté de communes de la Grande Vallée de la Marne published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.