Skip to main content

Public contracts of Communauté de communes de la Haute-Bigorre · 2025

Électricité

€67k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 12 August 2025 · ended around October 2026 · 14 months

That is at most ~€58k a year on average: a maximum too.

Company selected

Électricité Industrielle J. P. FaucheTravaux d'installation électrique dans tous locaux · registered office Montauban (82000) · headcount 1,000 to 1,999 employees · SIREN 308250570

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 18 by amount of the 30 contracts Communauté de communes de la Haute-Bigorre published for 2025.

Other contracts of Électricité Industrielle J. P. Fauche in Communauté de communes de la Haute-Bigorre

Restructuration des réseaux électriques industriels de l’abattoir…2019 · maximum over 3 months200€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 3

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.