Skip to main content

Public contracts of Communauté de communes de la Haute Comté · 2026

Mo et Iqoa réhab ouvrages SNCF t2 et 3 voie verte y

€109k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 28 May 2026 · running until about May 2029 · 3 yrs
Ongoing28 May 2029

That is at most ~€36k a year on average: a maximum too.

Company selected

PMMIngénierie, études techniques · registered office Dole (39100) · headcount 50 to 99 employees · SIREN 402402143

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Spielmann & Chirino Architectures. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.