Public contracts of Communauté de communes de la Vallée de la Doller et du Soultzbach · 2026

Extension du complexe sportif Roger Gaugler à Masevaux-Niederbruck

Électricité · Courants faibles

€75k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 11 February 2026 · running until about February 2028 · 2 yrs
Ongoing12 Feb 2028

That is at most ~€37k a year on average: a maximum too.

Who won it

ParelecTravaux d'installation électrique dans tous locaux · registered office Walheim (68130) · headcount 6 to 9 employees · SIREN 381622059

The competition

6 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 18 by amount of the 28 contracts Communauté de communes de la Vallée de la Doller et du Soultzbach published for 2026.

Other contracts of Parelec in Communauté de communes de la Vallée de la Doller et du Soultzbach

Périscolaire de burnhaupt-le-bas2022 · maximum over 16 months114€kConstruction d’un accueil périscolaire à Burnhaupt-le-Bas2022 · maximum over 16 months100€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.