Skip to main content

Public contracts of Communauté de communes de la Veyle · 2025

Maîtrise d’œuvre réhabilitation énergétique de l’ensemble bâti "salle polyvalente-restaurant scolaire"ainsi que la création d’une garderie périscolaire a…

€167k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 17 January 2025 · running until about April 2027 · 2.5 yrs
Ongoing19 Apr 2027

That is at most ~€74k a year on average: a maximum too.

Who won it

ProjelecIngénierie, études techniques · registered office Macon (71000) · headcount 10 to 19 employees · SIREN 344075015

A contract awarded to 3 holders; above, the main holder. With it: RBC Architecture, Technique et Construction - Teco (Teco Ingenierie Solutions - Teco Sodes - Teco Cwse - Teco Betecar - Teco HA8). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

22 bids received

Median for this procedure in 2025: 3 bids, across 17964 comparable contracts. Open tender · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 10 by amount of the 18 contracts Communauté de communes de la Veyle published for 2025.

Other contracts of Projelec in Communauté de communes de la Veyle

Maîtrise d’oeuvre pour la rénovation du gymnase de Mézériat2020 · maximum over 2 years103€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.