Skip to main content

Public contracts of Communauté de communes de Miribel et du Plateau · 2021

Construction du gymnase La Chanal

€720k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 24 February 2021 · ended around May 2022 · 15 months

That is at most ~€576k a year on average: a maximum too.

Company selected

Alpha ÉnergieTravaux d'installation d'équipements thermiques et de climatisation · registered office Beligneux (01360) · headcount 20 to 49 employees · SIREN 488400649

Number 8 by amount of the 62 contracts Communauté de communes de Miribel et du Plateau published for 2021.

Other contracts of Alpha Énergie in Communauté de communes de Miribel et du Plateau

Chauffage bois2021 · maximum over 15 months720€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.