Skip to main content

Public contracts of Communauté de communes de Miribel et du Plateau · 2021

Construction du gymnase La Chanal

€293k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 29 June 2021 · ended around March 2024 · 3 yrs

That is at most ~€106k a year on average: a maximum too.

Who won it

MargueronTravaux de charpente · registered office Belley (01300) · headcount 20 to 49 employees · SIREN 487449167

Number 16 by amount of the 62 contracts Communauté de communes de Miribel et du Plateau published for 2021.

Other contracts of Margueron in Communauté de communes de Miribel et du Plateau

Charpente bois2021 · maximum over 15 months293€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.