Skip to main content

Public contracts of Communauté de communes de Saint-Méen Montauban · 2024

Maîtrise d’oeuvre de travaux d’économies d’énergie au Cinéma le Celtic et Manoir de la Ville Cotterel

€19k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 4 March 2024 · ended around January 2025 · 10 months

Company selected

Iph IngenierieIngénierie, études techniques · registered office Rouvroy (02100) · headcount 50 to 99 employees · SIREN 321782781

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 22 by amount of the 24 contracts Communauté de communes de Saint-Méen Montauban published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Maîtrise d’oeuvre de travaux d’économies d’énergie au Cinéma le…: up to €19k over 10 months, Communauté de communes de Saint-Méen Montauban 2024 · Qipu