Public contracts of Communauté de communes de Thann-Cernay · 2024

Construction d’une crèche à Aspach-Michelbach, sous maîtrise d’ouvrage de la Communauté de communes de Thann-Cernay

Plafond suspendu

€23k
maximum contract amount over 20 months — what was paid on it is not published
Signed on 26 March 2024 · ended around November 2025 · 20 months

That is at most ~€14k a year on average: a maximum too.

Who won it

Isolation 68Travaux d'isolation · registered office Kingersheim (68260) · headcount 10 to 19 employees · SIREN 808901193

The competition

93 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 81 by amount of the 114 contracts Communauté de communes de Thann-Cernay published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.