Public contracts of Communauté de communes de Thann-Cernay · 2022
Maîtrise d’oeuvre pour la pose d’une conduite d’interconnexion Thann/Cernay
That is at most ~€8k a year on average: a maximum too.
Who won it
Berest Rhin RhoneIngénierie, études techniques · registered office Colmar (68000) · headcount 20 to 49 employees · SIREN 820961019The competition
Median for this procedure in 2022: 1 bid, across 111 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
Number 51 by amount of the 63 contracts Communauté de communes de Thann-Cernay published for 2022.
Other contracts of Berest Rhin Rhone in Communauté de communes de Thann-Cernay
Elaboration de la mise à jour du programme d’opération2025 · maximum over 3 months40€kÉtude de faisabilité de la neutralisation et gestion des…2024 · maximum over 7 months29€kMaîtrise d’oeuvre pour l’aménagement de deux itinéraires cyclables…2022 · maximum over 2 years55€kContract details (procedure, price, amendments, lots)
Procedure : Marché passé sans publicité ni mise en concurrence préalable
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.